Residents in parts of the Ashanti Region are expected to experience temporary power outages from Thursday, November 26, to Tuesday, December 1, 2026, as the Ghana Grid Company Limited (GRIDCo) undertakes an upgrade of a major transmission line.
In a notice issued on Saturday, November 21, the Electricity Company of Ghana (ECG) said the planned outages would allow GRIDCo to continue work on the Anwomaso-Ridge Bulk Supply Point transmission line.
The project involves replacing the existing 364MVA single-circuit transmission line with a modern double-circuit line rated at 2 x 488MVA, bringing the total capacity to 976MVA.
According to ECG, the outages will occur daily between 7:30 a.m. and 5:00 p.m. throughout the six-day period.
Areas to Be Affected
The communities expected to experience the outages include:
Ahenema Kokoben, Sokoban, Daban, Asaago, Ampabame No. 1 and 2, Bekwame, Kotwi, Nkoransa, Paa, Kyekyewere, Pakyi No. 1 and 2, Brofoyedru, Sabin Akrofuom, Adum Afrancho and Anyinam.
Other affected areas include parts of Santase, Atonsu Kuwait, Naachia, Sawuah, Aprabon, Adagya, Esereso, Feyiase and Zoomlion, as well as surrounding communities.
ECG said the transmission line upgrade forms part of ongoing efforts to improve electricity supply in the Ashanti Region.